Pool renovation and deck replacement update 8/11

On August 7, the electrical work passed inspection. The contractor is expected to be on site to backfill all the skimmers and trenches and begin installing the tile and coping this week. The tile and cooing will take about four days, followed by concrete deck framing and rebar installation. Once that work is complete, the contractor will call for another inspection.