After a lengthy permitting and contractor selection process, work has officially begun on redoing the pool house to improve the bathrooms, reclaim the unused sauna space, and fix the plumbing, safety, and accessibility issues. Both restrooms/changing rooms will be accessible from the front of the building. Outdoor showers are being added. Work is expected to take three to four months.


The galvanized water pipes are completely rusted and corroded inside leaving barely 1/4 inch for water to travel and increasing the risk of leaks.

We tested for asbestos and lead. The good news is only a small amount of asbestos was detected and only in the drywall tape in the water heater closet and under the paint in the office. It will be removed by qualified professionals.
We will keep you updated on the progress.